Building a report

Hello Community,

I want to see the log hours in below hierarchy manner and able to see log hours in every step. FYI : The epic doesn’t have log hours most of the time but the sub-tasks inside it have the log hours and those sub-task are linked but belong to other projects. Guyz do you think, it is possible to achieve this ?

Projects >> Epic Issues >> A group having few of people >> List of users

Regards,
Soumya Subudhi

Hi @Soumya_Subudhi

Try using the “Epic” hierarchy in the Issue dimension and expand the hierarchy to the desired levels. The measure “Hours spent” values will be summed up from the children’s issues to the parent. See an example in the picture below:

Please see the eazyBI documentation page regarding the data cube model, also explaining hierarchies - Data model - eazyBI for Jira.

In addition, please watch the eazyBI training video as well - Training videos - eazyBI for Jira.