Dynamic report for volume of work left on any given day

I have created a few calculated members in ‘Transition Status’ dimension and want to generate a dynamic report which would indicate the amount of work left based on original estimated hrs on a daily/weekly basis. Would appreciate any help here

hi,

The recommended way to track the remaining effort of the original estimates is to use the “Remaining estimate hours history” measure in the report. This solution works if the users track the remaining estimates in Jira when reporting the worklogs:

This measure shows the history of the remaining hours on the timeline: