Eazy BI Report - Time between statuses (for closed issues)

Hello Team.

My company has recently adopted the use of Jira and EazyBI, and I’m getting used to it yet.

I’d like to request your help to build one report very similar with “Average workdays in status”, but I just need to measure the completed issues. Therefore, I need to work with the completed issues and I need to know how many days those issues took to get into the statuses that I have on my board.

Do you know if that is possible, and how can I do that? I don’t know if there is a field that already do this or if I have to create a calculated field to do it.

Thanks Guys,

Hi @Will_Ribeiro,

In eazyBI, there are two Status dimensions:

In this case, if you are using the Average days in transition status measure, you would combine this with the Transition Status dimension to see how much time issues have spent in each status.
Additionally, you can select the Status dimension in Pages and filter to see data only for issues that are currently in, e.g., Done status.

Lauma / support@eazybi.com