# How to manually draw predicted completion lines in Version report

**URL:** <https://community.eazybi.com/t/how-to-manually-draw-predicted-completion-lines-in-version-report/6301>\
**Category:** Questions & Answers\
**Created:** [March 4, 2021, 8:35pm UTC](https://community.eazybi.com/t/how-to-manually-draw-predicted-completion-lines-in-version-report/6301 "2021-03-04T20:35:02Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Christian1](https://community.eazybi.com/letter_avatar_proxy/v4/letter/c/df788c/32.png) [@Christian1](https://community.eazybi.com/u/Christian1)\
**Post date:** [March 4, 2021, 8:35pm UTC](https://community.eazybi.com/t/how-to-manually-draw-predicted-completion-lines-in-version-report/6301/1 "2021-03-04T20:35:03Z")

</div>

Hello, I would like to draw a manual line with estimated velocity inside the standard Version report. I use a measure, which works quite ok in case the velocity stays same all time (for example 200points per Sprint). I would like to change the expected velocity in the graph (vacation, different team size,…). I changed the measure in a way, but unfortunately the line “jumps” from one section to the other.  
What am I do wrong here?

Example 200SP/sprint by default. In March 800SP/Sprint and in April 400SP per sprint.

This is my measure:

```
Case
when
  DateInPeriod(
    'Today',[Time].CurrentHierarchyMember)
then
   NonZero((
    [Measures].[Story Points resolved],
    [Time].CurrentHierarchy.DefaultMember))
When
 DateBetween(
    [Time].CurrentHierarchymember.StartDate,
    'Today', [Measures].[Predicted completion date])

  Then
  -- current progress
    NonZero((
    [Measures].[Story Points resolved],
    [Time].CurrentHierarchy.DefaultMember))
   +
      Case
      When DateBetween([Time].CurrentHierarchyMember.StartDate,'2021-03-01', '2021-03-20')
      Then
       800/10
      WHEN DateBetween([Time].CurrentHierarchyMember.StartDate,'2021-03-20', '2021-04-10')  
       THEN
       400/10
      ELSE
       200/10
      End
  
    *
    DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
End

```

My graph looks like this: (cyan line)

 ![Bild 2128](https://community.eazybi.com/uploads/default/original/2X/f/f6585806e76c6db26701d38a0eb2af0775dd8545.png)

I would expect to see s.th. like the purple lines. Why does my cyan measure jumps down at the end of the month?

Many thanks  
Christian

---

<div class="post-metadata">

**Author:** ![gerda.grantina](https://community.eazybi.com/user_avatar/community.eazybi.com/gerda.grantina/32/1994_2.png) [@gerda.grantina](https://community.eazybi.com/u/gerda.grantina)\
**Post date:** [March 18, 2021, 10:06am UTC](https://community.eazybi.com/t/how-to-manually-draw-predicted-completion-lines-in-version-report/6301/2 "2021-03-18T10:06:16Z")

</div>

Hi @Christian1 ,  
In your formula, current progress should accumulate results from previous periods so there is no drop in your predicted velocity.

That formula should look like this:

```
CASE
  WHEN
    DateInPeriod('Today',[Time].CurrentHierarchyMember)
  THEN
     NonZero(([Measures].[Story Points resolved],[Time].CurrentHierarchy.DefaultMember))
  WHEN
   DateBetween([Time].CurrentHierarchymember.StartDate,'Today', [Measures].[Predicted completion date])
  THEN
  ([Measures].[Story Points resolved],[Time].CurrentHierarchy.DefaultMember)
  +
    CASE 
      WHEN DateBetween([Time].CurrentHierarchyMember.StartDate,'2021-03-01', '2021-03-20')
      THEN
        ([Measures].[Story Points resolved],[Time].[2021].[Q1 2021].[Mar 2021].[Mar 20 2021]) 
        + 800/10
        * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
      WHEN DateBetween([Time].CurrentHierarchyMember.StartDate,'2021-03-20', '2021-04-10') 
      THEN 
        -- previous + new
        ([Measures].[Story Points resolved],[Time].[2021].[Q1 2021].[Mar 2021].[Mar 20 2021]) 
        + 800/10
        * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
        + ([Measures].[Story Points resolved],[Time].[2021].[Q2 2021].[Apr 2021].[Apr 10 2021]) 
        + 400/10
        * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
    ELSE
      -- + both previous + new
      ([Measures].[Story Points resolved],[Time].[2021].[Q1 2021].[Mar 2021].[Mar 20 2021]) 
      + 800/10
      * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
      + ([Measures].[Story Points resolved],[Time].[2021].[Q2 2021].[Apr 2021].[Apr 10 2021]) 
      + 400/10
      * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
      + 200/10 
      * DateDiffWorkDays('Tomorrow',[Time].CurrentHierarchyMember.NextStartDate) 
    END
END

```

best,  
Gerda // [support@eazyBI.com](mailto:support@eazyBI.com)