Import projects with activity during the las 6 months

Hi,

I would like to know if it is possible to import data from Jira to EazyBI for the projects that have had some activity during the last 6 months.

Thank you so much!

Hi, @EsterCap

Please, use Additional Filter in Import options. Read more about that here.

Define JQL query, for example:

  • activity during the last 6 months use JQL: updated >= -180d
  • data from last 12 month use JQL: created >= -365d

See the example below:

  • In Jira selected created >= -3d

  • EazyBI advanced settings added: created >= -3d

  • Only these three issues were imported in eazyBI:

Kind regards,
Ilze support@eazybi.com

1 Like