# Progress bar per initiative based on closed vs remaining underlying story points

**URL:** <https://community.eazybi.com/t/progress-bar-per-initiative-based-on-closed-vs-remaining-underlying-story-points/9863>\
**Category:** Questions & Answers\
**Created:** [June 22, 2022, 6:09pm UTC](https://community.eazybi.com/t/progress-bar-per-initiative-based-on-closed-vs-remaining-underlying-story-points/9863 "2022-06-22T18:09:35Z")\
**Posts on this page:** 1\
**Showing post:** 3

<div class="post-metadata">

**Author:** ![gerda.grantina](https://community.eazybi.com/user_avatar/community.eazybi.com/gerda.grantina/32/1994_2.png) [@gerda.grantina](https://community.eazybi.com/u/gerda.grantina)\
**Post date:** [June 30, 2022, 8:20am UTC](https://community.eazybi.com/t/progress-bar-per-initiative-based-on-closed-vs-remaining-underlying-story-points/9863/3 "2022-06-30T08:20:52Z")

</div>

Hi @drewwiseman,  
If the **Advanced Roadmaps** is used, you need to import **Parent Link** and **Epic Link** fields and then after the data import “Advanced Roadmap” hierarchy is created based on the Jira configuration (on the Cloud you need to enable the integration and add the hierarchy configuration, see [here](https://docs.eazybi.com/eazybi/data-import/data-from-jira-apps/advanced-roadmaps-custom-fields#AdvancedRoadmapscustomfields-JiraCloud)).  
Also, in this Community article you can learn more about [additional issue hierarchies](https://community.eazybi.com/t/how-to-create-an-additional-issue-hierarchy/9793).

After that you can create a custom measure in the Measure dimension to roll up the progress. See an example here using “Issues resolved %”: [Issue Epic Gantt Chart - Issues - Jira Demo - eazyBI](https://eazybi.com/accounts/1000/cubes/Issues/reports/78204-issue-epic-gantt-chart)

Kind regards,  
Gerda // [support@eazyBI.com](mailto:support@eazyBI.com)

---