Hi
I am trying to replicate the following Eazy BI sample Burn up reports for our project that has multiple Epics . All other measures work well but for the Burn up and Burn up story points . Ideally I should be getting a dotted line after I select the burn up /burn up story points measure . Please can anyone give me any pointers on how to fix this issue ? I am capturing the following fields while creating an Epic :
a) Assignee
b) Reporter
c)Labels
d) Actual start date
e) Target start date
f) Target end date
g) Team
h) Priority
Worth mentioning that Epics are not story pointed individually but the stories connected to the Epics are .
Link to the Eazy BI sample reports :
https://eazybi.com/accounts/1000/cubes/Issues/reports/198349-issue-burn-down-in-epic
https://eazybi.com/accounts/1000/cubes/Issues/reports/198360-story-points-burn-up-in-epic-over-time