We would like to construct a cumulated burndown or advancement chart combining different JIRA projects and boards.
We work in SAFe and we would like to visualize the advancement of the entire train, rather than just a singular team view.
Is this at all possible? If so, please share any tips or tricks.
Hi @Kara_De_Nil,
Yes, you may analyze Sprint’s commitment and progress across several sprints from different boards and projects.
There is one example in the eazyBI Demo account that is an excellent starting point: Active (multiple) sprints story points burn-down - Issues - Jira Demo - eazyBI.
In this report, you can pick multiple boards and project from the page filter or hand-pick multiple sprints.
There is a related Community topic with a more advanced solution on grouping Sprints by custom properties (for example, cycles or trains).