Calculate total of a Field in Gantt Chart with time

eazyBI does not have an option to show values (resource plane) in a Gantt. We create bars to show when any work starts and is planned to end.

You would like to use some Table chart with Time on Columns to plot an overview of resource plan. You can check out this community topic for an example formula:

The formula address Start date and End date and will split Original estimated hours between those two dates. You can use you custom meausre created isntead of Original estimated hours for this.

Daina / support@eazybi.com