Hi, here!
Sorry for my question if it was before.
I have a project “A” and a task on it. A project manager adds an estimation - 3h. A developer works and logs 5h in the end of the work. He didn’t estimate correctly before. How can I see this difference in 2h? And on all the project?
Now I create a calculated member but I see that the result isn’t correct:
Hi.
To get the Orginal esitmated hours please use the below code
DefaultContext((
[Issue].currentmember,
[Assignee].CurrentMember,
[Measures].[Original estimated hours]
))
To get the total hours logged, please use the below code
Case
When
Not ISEMPTY([Measures].[Average Worklog Delay (Hours)])
then
[Measures].[Hours spent]
Else
Null
End
To get the difference between estimated hours and logged hours, Please use
[Measures].[Original estimated hours] - [Measures].[Hours spent]