Cycle Time related to Story Points in specific periods

Is it possible to prepare a report that calculates Cycle Time for the specified conditions (as shown in the screenshot):

  • The time will be calculated from the status “DEV IN PROGRESS” to “DONE.” (in each project we have different statuses between dev in progress and done statuses)
  • In the PAGES area, there will be an option to filter by “PROJECTS” and “STORY POINTS.”
  • TIME will be displayed in rows.
  • The results in the rows can be obtained separately for: YEAR, QUARTER, and MONTH.
  • it would be great if only working days were counted

Hi @mwrobel,
Thanks for posting your question!
Have you considered using the Issue Cycles approach?
See Issue cycles documentation for more details on setting up custom cycles.
Once you have imported the issue cycles (where you have grouped all the statuses you want to consider counted), use the measure “cycle name workdays of resolved issues” to display the workdays. Or use the measure “Average cycle name workdays”.
Here is another community post about the issue cycles, you may find useful - Add values in the fields - #2 by Marita_Norvele

Best wishes,

Elita from support@eazybi.com

Cool! Thank you, it works :wink: