EazyBI Gantt chart: Adding a timeline

Hello,

I created a Gantt chart in EazyBI jira.

Currently there is a timeline (Current Date), I would like to know if it is possible to add a second timeline in a Gantt chart as a milestone.

Thanks in advance.

1 Like

Hi @vicente_piedras,

Currently, it is not possible to add another timeline to the Gantt chart in eazyBI. We do have an improvement in our backlog regarding this. I added your vote to it.

Best,
Roberts // support@eazybi.com

Please can you add my vote to this feature please?

Thanks

Hi @Pedriel,

I added your vote :white_check_mark: !

Best,
Roberts // support@eazybi.com