I am trying to create a report that can show me a burn down for any epic individually within my project based on the original estimated hours.
The timeframe for the guideline should be the epic start /end date.
Instead of using the epic link I want to use the Advanced Roadmap Epic.
Sometimes better late than never. I hope @LFK got the needed report for the Epic burn-down, and this message is more for future readers who have a similar use case.
The report shows an epic timeline based on calculated start and end dates, but you can adjust it to use any dates on the Epic, like the Target start and Target end.
You can also build a similar report for other parent-level issues, like Features and Initiatives. The concept remains the same.