I want create a calculated measure that retain remaining estimate hours for sub-task when sprint start.
But I see this problem:
"The main problem is the lack of Sprint change history for issue sub-tasks in JIRA, as information from issue change log is used to calculate total Sprint scope.
Sub-task updated date is not changed when its parent issue Sprint information is changed;
also, sub-task sprint change history is not saved in its change-log.
We have opened the issue in Atlassian support, but it was closed as duplicated. Original issue https://jira.atlassian.com/browse/GHS-11459 8 by Structure is not resolved yet.
At the moment, only rough workarounds are possible, but they could be very slow and complicated (it requires many iterations in MDX).
Martins / eazyBI support"