Find the number of issues added to sprint after starting sprint

Hi
I want to create the report to show the list of issues planned during planning session (and got story point) vs number of issues added to sprint backlog after starting sprint( as unplanned tasks).
The diagram will be like a pie chart which shows number of planned vs unplanned issues.
Can you please help on this
Thanks

Hi @Behzad_Nazarbakhsh ,
You can use Jira Software sprint measures to get issues that are committed to the sprint at the start of the sprint or added later (see measures “Sprint issues committed” and “Sprint issues added”): Jira Software custom fields

Here you can see a demo report using those measures: Sprint issue balance - Issues - Jira Demo - eazyBI

best,
Gerda // support@eazybi.com