Gantt Chart by Project instead of Epic

Hello - How do we List Projects in Timeline instead of Epics?

Like below hierarchy…

[-]Project
[-]Epic
[-]Epic -1
[-]Epic -2
[+]Story/Task

Using the following report

https://eazybi.com/accounts/1000/cubes/Issues/reports/78204

Hi @rajaravanan,

You can slightly adjust the “Issue Epic Gantt Chart” for showing also Project level.

  1. In the “Issue” dimension, select to show Project level and then expand data to Epic or Story level in the report as you need.

  2. Remove filter “Issue epic link status matches In Progress” as it would hide Project level from report rows.

Best,
Zane / support@eazyBI

Thank you Zane. It worked! :slight_smile: