I would like to know if it is possible to aggregate all assigned (committed) story points to a Sprint that hasn’t commence yet. Not the backlog. The Sprint has already been created and has issues in it.

Thanks,

M.

Hi @Miguel_Blanca,

You could use the Story points created measure. Even if the Sprint is not started yet, this measure shows total Story points for the current Sprint the issue is in.

Another option is to use the Story points history measure, see an example report in eazyBI demo account. Please note that this report uses the Time within Sprint, which can be calculated only if Sprint planned or actual start and end are specified; if not, you probably should remove this filter for your report.