I would like to recreate the Progress bar (Epic level) from the Advanced Roadmap in eazyBI, is it possible? If so, how?
Hi @HRivest,
Thanks for posting your question.
I am answering a similar question here (I illustrate the answer with an example at an Epic level): Parent % completion based on child status, aggregated - #2 by Marita_Norvele
I hope this helps.
Best,
Marita from support@eazybi.com
Thanks Marita! I was able to create it… Now, I would like to filter it to only see the Epic (or Parent) that are not at 100% Done.
I think a calculated member could assist in this… But it requires a lot of variables, and I’m still having trouble to grasp set and tuple.
So I have a list of different projects (some are epics, some are stories), those are part of the issue dimension.
I want to Filter them based on the overall status of the parent.
If the status of said parent is Done, I don’t want to see them in the report. So I know I need an Except function in there.