How to report on subtasks hours?

Hello All!

Looking to create a report that displays Issues and related substasks that would display Original estimated hours, Hours spent, and Hours remaining.

Thank you all in advance!

Hi,

The first thing to try is to use the Sub-task issue hierarchy with respective measures:

The following formula shows at the parent level the hours spent on all sub-tasks (not including the parent itself):

([Measures].[Hours spent],
[Issue Type.By type].[Sub-Task])

Kindly,
Janis, eazyBI support