Looking for Kanban services (our Kanban swimlane jqls) WIP, formula for cycle/lead time and throughput (AVG. CYCLE TIME = AVG. WIP / THROUGHPUT). How to calculate these
Flow: To manage flow, we are going to monitor three Kanban metric:
a. Work In Progress (the number of items that we are working on at any given time)
b. Cycle Time (Lead Time) (how long it takes each of those items to get through our process).
c. Throughput (how many of those items complete per unit of time).
i. Little’s Law: AVG. CYCLE TIME = AVG. WIP / THROUGHPUT.
Figure 6: Little’s Law
Hello @randponting ,
Check this: Kanban project overview - Issues - Jira Demo - eazyBI
(fyi, all reports in Demo account here Analyze - Jira Demo - eazyBI can be exported then imported in your account and all calculated measures and tricks will be available for you!)
Kind regards,
Vasile S.
1 Like