Hello people,
As part of a more complex report, I want to calculate the sum of ‘Remaining estimate’ for issues added to a sprint after it started, at the time they entered the sprint. I can’t seem to work this one out. Has anyone else experienced this issue?
Hi @d.kamposos
You can use the Sprint remaining estimated hours added measure - Jira Software custom fields
The remaining estimated hours are captured at the moment when the issue was added to the sprint.
Let me know if this fits your use case!
Best regards,
Nauris / eazyBI support