Work Scope Measure in Active (multiple) sprints story points example chart

Utilizing the Active (multiple) sprints story points burn-down example chart. I’ve incorporated the example Work Scope measure into the aforementioned chart. While Work Scope measure works nicely in individual Sprints, note the Work Scope deep “V” in the between the Sprints. How can I correct this?

Hi @AWPPMT ,

The ​Work Scope measure is built to show the relevant story points for the active sprint and provide the Sprint story points at closing on the sprint closure date.
​When multiple closed sprints are selected, the same measure returns Story points history most of the time, but Sprint issues at closing on the individual sprint closing dates.
​You might use the measure “Story points history” instead to see a smooth line.