Are sprint actual start/end used in sprint metrics

When doing sprint metrics, are the actual start and end used as opposed to the planned start and end? If not, how can we report metrics on a sprint actual start and actual end?

We are using version 5.3.2 but will be migrating to cloud in the next 60 days.

@leslie

Yes, eazyBI would import few Sprint-related dates automatically, but that would require the most recent eazyBI version. It looks like you have 5.3.2 where not all of these pre-defined measures are available.

Please find the documentation page on sprint scope measures:
https://docs.eazybi.com/eazybijira/data-import/data-from-jira-and-apps/jira-software-custom-fields#JiraSoftwarecustomfields-Sprintscopemeasures

You can upgrade now or wait for the migration to Cloud. eazyBI cloud customers always have the most recent version.

Martins / eazyBI