Sum Hours Spent in the Last Two Sprints
|
|
1
|
11
|
February 28, 2025
|
Sprint velocity chart issue
|
|
2
|
19
|
December 9, 2024
|
Aggregating sprint data over multiple sprints in different projects
|
|
4
|
45
|
October 17, 2024
|
Sprint report that shows issues by epic and sprint measures such as points added, removed, resolved and completion
|
|
1
|
69
|
August 19, 2024
|
Hour spent in sprint for logged by users
|
|
2
|
42
|
August 9, 2024
|
As a Senior Scrum Master, I would like generate a eazyBI report to display all the boards and the sprints created for each board in a Jira Project so that i can see how many sprintgs each team has planned ahead.
|
|
1
|
35
|
August 5, 2024
|
Count number of times there were scope changes in the Sprint
|
|
2
|
127
|
July 17, 2024
|
Geting the US complete date even when it was not in the selected sprint
|
|
1
|
40
|
June 7, 2024
|
Calculate only Hours Spent of completed items in a Sprint
|
|
3
|
771
|
April 23, 2024
|
Finding the end date for the active Sprint
|
|
7
|
1761
|
February 16, 2024
|
Last Sprint Name, Start Date and End Date
|
|
5
|
530
|
February 9, 2024
|
Build sprint velocity report per custom field not per story points done
|
|
1
|
233
|
January 30, 2024
|
How many times the issue has been moved in a sprint
|
|
1
|
222
|
December 28, 2023
|
Active Sprint End Date
|
|
1
|
199
|
November 23, 2023
|
How to show how many times an issue was moved to next sprint?
|
|
1
|
223
|
November 15, 2023
|
Exclude Current Month from Measure Calculation
|
|
2
|
320
|
November 13, 2023
|
Story Points for committed issues which transitioned to other status
|
|
1
|
325
|
November 2, 2023
|
EazyBI count sprints linked to Jira board
|
|
4
|
272
|
October 9, 2023
|
Issues from specific project no longer show in eazy BI
|
|
1
|
408
|
October 6, 2023
|
How could I build report to show sprint's scope change over time?
|
|
1
|
431
|
September 7, 2023
|
Calculating rolling average velocity for each sprint
|
|
3
|
1875
|
August 29, 2023
|
How can i get a burn down chart for all my sprints
|
|
2
|
242
|
August 17, 2023
|
Can we find out which issues were moved from one sprint to another?
|
|
20
|
16379
|
July 7, 2023
|
How to show how much story points Developer resolved by the sprint?
|
|
2
|
634
|
June 19, 2023
|
Need help with getting count of total issues on any specific day
|
|
1
|
393
|
May 25, 2023
|
Total time spent of issues within sprint
|
|
5
|
2251
|
May 2, 2023
|
How to show in single table sprint issue committed, completed, removed, added after for 3 teams
|
|
1
|
286
|
April 18, 2023
|
Get time spent for issues that were added later in the sprint
|
|
9
|
691
|
March 30, 2023
|
Sprint Start and Actual Start are the same
|
|
3
|
585
|
March 29, 2023
|
Sprint metrics based on planned end date, not sprint closure
|
|
1
|
342
|
March 2, 2023
|