Hi. We are using SAFe approach including Program Increments consisting of 3 sprints. Is there any way to create new time hierarchy member, e.g. “PI” name where:
the first Program Increment starts by specific date
the Program Increment consists of 3 sprints, where 1 sprint duration is 3 weeks = 9 weeks
Example: the PI1 starts by 2020-10-12 and PI2 starts after 9 weeks, P3 starts after 18 weeks etc.
eazyBI does not have default support for Time hierarchies with such long periods. You can define custom Time hierarchies using 2,3,4 week periods, though.
You can consider defining a new custom Time hierarchy with 3 week period to represent Sprint cycles. Then you can define PI members as calculated members using those new Sprint cycles.
Define a new custom time hierarchy with 3 weeks and 2020-10-12 as a start date to get correct cycles: